A number of components such as storm drain B, storm drain locking devices and other equipment will be used when installing the aluminum alloy drain system gutter. Below, small Bo for you to introduce the installation of aluminum alloy gutter content.
First, storm drain (gutter) installation:
1. Level the installation position of the rain sink, and ink the wire from beginning to end.
2. Take the storm drain out of the bag, place the storm drain smoothly on the ground or scaffolding, install the rain barrel horizontally under the storm drain, and use a cutting machine to cut out the hole with the same 。
3. Slowly put the rain barrel into the rain tank until the water is in place.
4. Install the hanger on the rain sink, place it in order, and master the spacing. The distance between the two adjacent hangers is 40~45cm.
5. Use an electric drill (No. 6 drill bit) to drill holes at the clip position at a distance of 40 to 45 cm, and then knock in the expansion tube.
6. Place the aluminum alloy gutter on the elastic position, adjust the spacing of the "hanger", and then use the "hanger" button to adjust the spacing of the "hook". Secure hangers and storm drains with 4x40
stainless steel screws.
7. When encountering the corner of the rain sink, it is necessary to use the "connector" to connect the two corners of the "Yang" and "Yin", and the connection part between the rain sink and the rain sink also needs to use the "connector" to connect.
8. During the installation of the rain sink, in order to avoid water leakage, the corresponding accessories such as the locking device and joints should be coated with glass glue and PVC glue.
Second, rainwater pipe (square pipe) installation:
1. Take the rainwater pipe out of the packaging bag and place it on the ground or scaffolding.
2. Hang the plumb weight on the downdraft pipe of the rain sink so that it is perpendicular to the ground, and select the anchor point in the vertical position to maintain the spacing.
3. Use an electric drill to drill holes at the anchor points, and then knock in the expansion tube.
4. In the position of the rain barrel, use the "drainage device" to lead the square rain pipe to the inside, close
to the wall and vertically downwards, fixed with a locator, and master the spacing; Drain device for left and right sides? Fixed with 3x10 stainless steel screws.
5. The drainage device and the connector are bonded with polyvinyl chloride adhesive or glass adhesive.
Consulting telephone: